Hagfors Center stairwell curtainwall installation begins this week

submitted by rjohn@augsburg.edu

As the weather helps construction crews make progress on the final layer of the Hagfors Center roof, crews prepare the steel structure on the stairwells and lobby for installation of the glass curtain wall in the coming weeks. This week’s summary of construction activity on the Hagfors Center includes a photo of crews preparing the steel structure on the west staircase to support installation of the glass curtainwall, as well as updates on the following:

[1] Stairwell work
[2] Rooftop greenhouse, including a photo of the greenhouse base, under construction
[3] Lobby exterior
[4] Roof work, including a photo of crews installing the white, reflective roof layer
[5] Window frames and glass
[6] Precast exterior

See the full construction update for the week of February 13, 2017