submitted by sitarami@augsburg.edu
MnDOT is shifting the schedule to install the beams for the temporary bridge over I-94 at 22nd Avenue.
MnDOT reports: We had planned on a weekend closure Nov. 8-11. That is canceled. Crews will do the beam installation work overnight this week. Here are the new date and times:
MnDOT will be closing I-94 in both directions Tuesday and Wednesday overnight.
10 p.m. Tuesday, Nov. 5 to 5 a.m. Wednesday, Nov. 6. I-94 is closed in both directions between I-35W and Highway 280. Detour is I-35W, Highway 36 and I-35E
10 p.m. Wednesday, Nov. 6 to 6 a.m. Thursday, Nov. 7
I-94 is closed is both directions between I-35W and Highway 280. The detour is I-35W, Highway 36 and I-35E.
We are also making good progress on the 25th Avenue bridge repairs. We expect to be done earlier than planned. We will let you know when that work is finished and the overnight closure of I-94 west is no longer needed.
Please check http://www.511mn.org for real-time updates. All closures are weather permitting and subject to change.